The initiation phase typically ends:
A) when there is sufficient information to begin developing a detailed schedule and budget.
B) once the project manager has been chosen.
C) after project execution resources such as office space and computers) have been acquired.
D) when the project scope has been clearly defined and all stakeholders are in agreement.
E) once the punch list has been completed.
Correct Answer:
Verified
Q24: The emphasis of the _ phase is
Q25: Confirming or developing conceptual schedules and budgets
Q26: Project execution resources, such as office space,
Q27: In the case of a complex construction
Q28: What is a punch list?
A) A list
Q30: Which of the following statements is true
Q31: The four major phases of a project
Q32: Project documents are archived during the _
Q33: In the case of an information technology
Q34: During the _ phase the client takes
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents