Question 54

Multiple Choice

In terms of stakeholder agreement, which of the following does NOT increase the complexity of a project?


A) An increase in the number of stakeholders
B) The inability of stakeholders to influence project outcomes
C) The emotional investment of the stakeholders in the project
D) The ability of the stakeholders to influence the project execution approach
E) The degree to which the project stakeholders disagree