Which of the Following Changes Will NOT Likely Change the Scope

Question 44

Multiple Choice

Which of the following changes will NOT likely change the scope of the project?


A) Changes in the marketplace
B) Changes in the timing of the product delivery
C) Changes in the product design
D) Changes in the HR policies of the parent organization
E) Changes in the financial health of the client

Correct Answer: