A contractor was feeling defeated because the job he was working on was so far behind schedule. As he looked at the job site, he saw one worker moving bricks by carrying two at a time from where they were unloaded to where they were needed. He saw another climbing up a ladder with a few shingles, climbing back down to get more, and then repeating the process. Which management process could be used to determine how the workers could perform their tasks more efficiently?
A) Time and motion studies
B) Resource assessments
C) Workload analyses
D) Systems analyses
E) Cost-benefit analyses
Correct Answer:
Verified
Q3: Frank and Lillian Gilbreth are important to
Q4: How did the Industrial Revolution change jobs
Q13: Technological management involves managing the production of
Q25: Which of the following statements about the
Q26: Prior to the development of scientific management
Q28: One of the advantages of a systems
Q31: Which of the following is NOT part
Q32: According to the systems approach to management,
Q33: The contingency approach to management holds that
Q33: The goal of scientific management is to_
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents