Under the percentage-of-completion method, a company has recognized $40,000 of profit through to the beginning of the current year on a contract, and total estimated contract cost is $500,000 at that time. The contract price is $800,000. What is the percent of completion at the beginning of the current year?
A) 13.33%
B) 15.8%
C) 8%
D) Insufficient data
Correct Answer:
Verified
Q107: Which of the following would be
Q108: A firm uses the instalment method of
Q109: A firm uses the instalment method of
Q110: A construction company uses the percentage-of-completion
Q111: Given the following data, what is
Q113: A construction company has contracted with a
Q114: When progress billings are sent on
Q115: The completed contract method of accounting for
Q116: The percentage-of-completion method of accounting for long-term
Q117: The January 1, 2006 status of long-term
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents