A Construction Company Has Consistently Used the Percentage-Of-Completion Method of Recognizing

Question 134

Essay

A construction company has consistently used the percentage-of-completion method of recognizing income. In 2007, the company started work on a $6,000,000 construction contract, which was completed in 2008. The accounting records disclosed the following data: 20072008 Progress billings $3,800,000$2,200,000 Estimated cost to complete as of 12/313,600,0001,800,000 Billings to the government during the year 4,600,0001,400,000 Cash collected during the year 3,600,000\begin{array} { | l | l | l | } \hline & \mathbf { 2 0 0 7 } & \mathbf { 2 0 0 8 } \\\hline \text { Progress billings } & \$ 3,800,000 & \$ 2,200,000 \\\hline \text { Estimated cost to complete as of } 12 / 31 & 3,600,000 & 1,800,000 \\\hline \text { Billings to the government during the year } & 4,600,000 & 1,400,000 \\\hline \text { Cash collected during the year } & & 3,600,000 \\\hline\end{array} Calculate the amount of income that should have been recognized in 2007.

Correct Answer:

verifed

Verified

blured imageGross profit to be r...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents