During the Implementation of Project Termination,the Termination Manager Should Ensure

Question 16

Multiple Choice

During the implementation of project termination,the termination manager should ensure that __________.


A) delivery and implementation of project results were accomplished regardless of termination method
B) formal acceptance of the project is obtained from the project team
C) formal acceptance of the project is acknowledged by the client
D) the project's documentation is shredded