Which of the following conventions has the characteristic of the project always seeming to be running late,until the very end when it seems to suddenly catch up?
A) The 50-50 rule
B) The 0-100 percent rule
C) Critical input use rule
D) The proportionality rule
Correct Answer:
Verified
Q26: If EV = $500,AC = $475,PV =
Q27: If EV = $500,AC = $450,PV =
Q28: There are several conventions used to aid
Q29: In earned value analysis,the _ is computed
Q30: If EV = $500,AC = $475,PV =
Q32: In earned value analysis,if the cost variance
Q33: If EV = $500,AC = $450,PV =
Q34: In earned value Analysis,the 50-50 rule assumes
Q35: _ can often give the project manager
Q36: EV - PV = _.
A)SV
B)CV
C)CPI
D)TV