When collecting raw project data,it is important to make sure that all data are collected from sources that operate on the same __________ and with the same rules for data collection.
A) continent
B) floor of the building
C) time intervals
D) scope plan
Correct Answer:
Verified
Q6: The project _ describes what is being
Q19: _ is collecting,recording,and reporting information concerning any
Q20: Monitoring,as an activity,should be kept distinct from
Q24: If CPI = 1.05,then _ is favorable.
A)time
Q26: Ordinal rankings of performance are examples of
Q26: If EV = $500,AC = $475,PV =
Q27: If EV = $500,AC = $450,PV =
Q29: In earned value analysis,the _ is computed
Q31: Which of the following conventions has the
Q36: EV - PV = _.
A)SV
B)CV
C)CPI
D)TV