If the appropriate scheduling equation for task A of a project were W = D * U,and it was initialized so that W = 40d,D = 10d,and U = 4 resources,and task A is an effort-driven activity,correctly balance this equation if the value for U is changed from 4 to 5.To balance the equation,the altered variable and its new value are __________.
A) D = 6w
B) W = 6d
C) D = 8d
D) W = 6d.
Correct Answer:
Verified
Q4: One cannot save _,rather one can only
Q8: _ describes the amounts of individual resources
Q9: _ times result from an attempt to
Q12: A project task is said to be
Q13: The use of _ activity time estimates
Q29: Studies have shown that the _ scheduling
Q37: In some situations,two activities are scheduled to
Q39: Three important parameters used to assess the
Q40: _ aims to minimize the period-by-period variations
Q52: With respect to project scheduling,_ is the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents