Given W = D * U for an effort-driven task.Assume an 8-hour workday.Initially,task R was assigned to Bob.Bob was expected to accomplish 32 hours of work in five days.Bob was expected to be 100% available to work on task R during the entire five days.However,Bob left the company and will be replaced by Sam.Sam's efficiency rate is 90%.If Sam is only 70% available,Sam will require __________ hours to complete task R.
A) 63
B) 40
C) 53.2
D) 50.8
Correct Answer:
Verified
Q1: The two principles to follow when crashing
Q3: When we change technology,we may also be
Q12: A project task is said to be
Q18: The standard practice with AOA and AON
Q22: Given a scheduling equation W = D
Q26: Given that task A will use three
Q28: Thoughtless optimism,the "student syndrome," and multitasking to
Q37: In some situations,two activities are scheduled to
Q39: Three important parameters used to assess the
Q40: _ aims to minimize the period-by-period variations
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents