Project task E has the following estimates: (1) optimistic time - 10 days,(2) Pessimistic time - 20 days,and (3) Most likely time - 12 Days.The standard deviation for time using the beta statistical distribution is ________ days.
A) 2
B) 1) 5
C) 2) 33
D) 1) 67
Correct Answer:
Verified
Q6: The authors,when discussing networks,describe a(n)_ as the
Q8: A(n)_ is a specific task or set
Q26: The shortest time in which the entire
Q29: When using the beta distribution,the denominator of
Q40: The _ chart shows planned and actual
Q41: A _ is a combination of interrelated
Q42: The line connecting two nodes is referred
Q48: A clearly identifiable point in a project
Q49: Any time two or more paths of
Q52: _ is one possible way to check
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents