You have been asked to estimate the costs for a project to build an industrial power plant.Based on historical data,the steam turbine accounts for 30 percent of the total costs for the plant.If the steam turbine costs $300,000,the expected top-down estimated cost for this project would be __________.
A) $1,000,000
B) $100,000
C) $10,000
D) $900,000
Correct Answer:
Verified
Q2: A budget strategy that is based on
Q7: The advantage of the_ process is that
Q17: The _ charge is composed of the
Q19: _ are where the defined responses to
Q23: A work element in the project plan
Q24: Suppose that a person requires eight hours
Q24: Each time the output doubles,the worker hours
Q26: Suppose that a person requires 60 minutes
Q33: Given a project salary cost of $400,000
Q46: Identify some of the common problems faced
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents