Earned Value tells us __________
A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) None of the above
Correct Answer:
Verified
Q2: A cost variance (CV) can be positive
Q11: The project communications plan may be informal
Q14: The schedule variance (SV) shows the difference
Q20: Internet and Web-Based technologies have a significant
Q21: Cost Variance CV= Earned Value - _.
A)Budget
Q24: A _ is a formal or informal
Q26: In Project Communications Management,getting the right information
Q27: If you hired a consulting firm to
Q33: Cost Variance (CV) is _
A) how much
Q35: Expected Time to Completion (ETC) is _
A)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents