Cost Variance (CV) is __________
A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) the difference between the estimated cost and how much we have actually spent
Correct Answer:
Verified
Q28: The total planned cost of the project
Q29: Budget At Completion (BAC) is _
A) how
Q30: EV-AC =
A) Cost performance index (CPI)
B) Scheduled
Q31: If you hired a consulting firm to
Q32: The budgeted cost of work scheduled for
Q34: Earned Value tells us _
A) how much
Q35: Expected Time to Completion (ETC) is _
A)
Q36: Barring a change in project scope and
Q37: A metric that provides an estimate for
Q38: Actual Cost (AC) is _
A) how much
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents