Estimate at Completion (EAC) is __________
A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) how much we spent to complete the project
Correct Answer:
Verified
Q35: Expected Time to Completion (ETC) is _
A)
Q36: Barring a change in project scope and
Q37: A metric that provides an estimate for
Q38: Actual Cost (AC) is _
A) how much
Q39: If we know the Actual Cost of
Q41: Describe how the SPI and CPI can
Q42: What is a project review and what
Q43: Describe the concept of earned value.
Q44: Why is communications among project stakeholders so
Q45: What is a forecast report?
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents