The metric that provides an estimate of the most likely total or final cost of the project based on the project's performance and any risks that should be considered is the:
A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
Correct Answer:
Verified
Q22: Barring a change in project scope and
Q23: The cost incurred for completing a scheduled
Q24: A _ is a formal or informal
Q25: Cost Variance (CV) = Earned Value -
Q26: A _ shows how the scope, features
Q28: The total planned cost of the project
Q29: Budget At Completion (BAC) is _
A) how
Q30: EV-AC =
A) Cost performance index (CPI)
B) Scheduled
Q31: If you hired a consulting firm to
Q32: The budgeted cost of work scheduled for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents