Under the Precedence Diagramming Method,the most common relationship between two activities which implies a logical sequence is called:
A) Finish-To-Start FS)
B) Start-To-Start SS)
C) Finish-To-Finish FF)
D) Start-To-Finish SF)
E) none of the above
Correct Answer:
Verified
Q25: The technique used to find the sequence
Q26: Starting the next task before the first
Q27: The Critical Path is:
A) the longest path
Q33: Completing activities in parallel is called_
A) slacking.
B)
Q35: _ is well suited for developing simulations
Q37: Installing the operating system on a computer
Q41: The final step in determining the cost
Q44: Critical Chain Project Management CCPM)is based on
Q64: What is meant by slack (or float)?
Q72: How can parallel activities help shorten the