Under the Precedence Diagramming Method,the situation which occurs when two activities can start at different times,have different durations,but are planned to be competed at the same time is called:
A) Finish-To-Start FS)
B) Start-To-Start SS)
C) Finish-To-Finish FF)
D) Start-To-Finish SF)
E) none of the above
Correct Answer:
Verified
Q3: A parallel activity is a task that
Q10: Installing a server before loading the operating
Q13: The critical path is the shortest path
Q15: Predecessor activities are activities that can be
Q19: An over allocated resource would arise when
Q23: Under the Precedence Diagramming Method,the situation which
Q26: Under the Precedence Diagramming Method,the least common
Q28: Adding resources to an activity to shorten
Q31: The technique used to help manage the
Q38: _ is considered the most useful and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents