Which of the following statements about the work breakdown structure WBS) is not ?
A) The WBS provides a hierarchical structure that outlines the activities or work that needs to be done in order to complete the project scope.
B) The WBS should support the project's MOV
C) The WBS should be developed by the project manager.
D) The WBS provides a framework for developing a tactical plan to structure the project work.
E) The WBS provides a bridge or link between the project's scope and the detailed project plan
Correct Answer:
Verified
Q6: The work breakdown structure (WBS) decomposes, or
Q7: Because function points are independent of technology,they
Q8: A tangible and verifiable piece of work
Q12: The 100 percent rule is the most
Q13: The use of heuristics is based following
Q16: The three major factors in estimating an
Q22: The Delphi technique is a quick and
Q25: Time boxing involves allocating a time segment
Q30: According to the text, most real-world estimating
Q35: The PMBOK area called project time management
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents