Heiny Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed to cost of goods sold at the end of the month. In March, the company completed job G59N that consisted of 21,000 units of one of the company's standard products. No other jobs were in process during the month. The job cost sheet for job G59N shows that the job's total cost was $940,800. During the month, the actual manufacturing overhead cost incurred was $269,640 and the manufacturing overhead cost applied was $249,900. And during the month, 6,000 completed units from job G59N were sold. No other products were sold during the month. The unadjusted cost of goods sold (in other words, the cost of goods sold BEFORE adjustment for any underapplied or overapplied overhead) for March is closest to:
A) $871,500
B) $274,440
C) $940,800
D) $268,800
Correct Answer:
Verified
Q42: The Donaldson Company uses a job-order costing
Q43: Molano Corporation has provided the following data
Q44: Falwell Inc., which uses job-order costing,
Q45: Heminover Inc., which uses job-order costing, has
Q46: Lietz Corporation has provided the following data
Q48: Araiza Inc. uses a job-order costing system
Q49: Gest Inc. has provided the following data
Q50: The actual manufacturing overhead incurred at Hogans
Q51: Burghardt Inc. uses a job-order costing system
Q52: Watwood Inc. uses a job-order costing system
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents