Martinez Aerospace Company uses a job-order costing system.The direct materials for Job #045391 were purchased in July and put into production in August.The job was not completed by the end of August.At the end of August,in what account would the direct material cost assigned to Job #045391 be located?
A) Raw materials inventory.
B) Work-in-Process inventory.
C) Finished goods inventory.
D) Cost of goods manufactureD.The uncompleted job would be located in Work-in-Process.
Correct Answer:
Verified
Q5: In a job-order costing system,direct labor cost
Q13: What document is used to determine the
Q15: Which of the following is the correct
Q38: The balance in the Work in Process
Q49: Which of the following accounts is debited
Q84: Sharp Company's records show that overhead was
Q85: Scottso Corporation applies overhead using a normal
Q86: Which of the following is correct with
Q90: Which terms will make the following statement
Q97: In computing its predetermined overhead rate,Marple Company
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents