Developing Standards
Cold Queen Company is a small producer of fruit-flavored frozen desserts. For many years, Cold Queen's products have had strong regional sales on the basis of brand recognition; however, other companies have begun marketing similar products in the area, and price competition has become increasingly important. John Wakefield, the company's controller, is planning to implement a standard cost system for Cold Queen and has gathered considerable information from his co-workers on production and materials requirements for Cold Queen's products. Wakefield believes that the use of standard costing will allow Cold Queen to improve cost control and make better pricing decisions.
Cold Queen's most popular product is raspberry sherbet. The sherbet is produced in 10-gallon batches, and each batch requires six quarts of good raspberries. The fresh raspberries are sorted by hand before entering the production process. Because of imperfections in the raspberries and normal spoilage, one quart of berries is discarded for every four quarts of acceptable berries. Three minutes is the standard direct labor time for sorting to obtain one quart of acceptable raspberries. The acceptable raspberries are then blended with the other ingredients; blending requires 12 minutes of direct labor time per batch. After blending, the sherbet is packaged in quart containers. Wakefield has gathered the following pricing information:
• Cold Queen purchases raspberries at a cost of $0.80 per quart. All other ingredients cost a total of $4.50 per 10-gallon batch.
• Direct labor is paid at the rate of $9.00 per hour.
• The total cost of material and labor required to package the sherbet is $0.38 per quart.
Required:
a. Develop the standard cost for the direct cost components of a 10-gallon batch of raspberry sherbet. For each direct cost component of a batch of raspberry sherbet, the standard cost should identify the
(i) Standard quantity.
(ii) Standard rate.
(iii) Standard cost per batch.
b. As part of the implementation of a standard cost system at Cold Queen, John Wakefield plans to train those responsible for maintaining the standards in the use of variance analysis. Wakefield is particularly concerned with the causes of unfavorable variances.
(i) Discuss the possible causes of unfavorable materials price variances and identify the individual(s) who should be held responsible for them.
(ii) Discuss the possible causes of unfavorable labor efficiency variances and identify the individual(s) who should be held responsible for them.
Correct Answer:
Verified
Q1: Establishing a Standard Cost System
The Tipy Canoe
Q2: Basic Price and Quantity Variances for
Q4: Assignment of Decision Rights for Setting Standards
Attendant
Q5: Standard costs embody targets. The targets should:
A)be
Q6: Fegox Firinghi (FF) produces flip flops. Each
Q7: Barb Bubbletop (BB) produces bangles. Each bangle
Q8: Hospital Software sells and installs computer
Q10: What is the typical treatment of large
Q10: Differences between Lean Manufacturing and Standard Costing
Lean
Q11: A review of skilled engineering labor rates
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents