LS - latest start time can be defined as:
A) equal to the earliest start time for the activity plus the time required to complete the activity.
B) equal to the earliest start time for the activity plus the time required to complete the activity
C) equal to the latest finish time minus the time required to complete the activity.
D) the earliest time at which the activity can start given that its precedent activities must be completed first.
Correct Answer:
Verified
Q38: Gantt charts (or Bar charts) are useful
Q39: The CPM network consists of arcs and
Q40: The CPM establishes:
A) The quantity of work
Q41: The critical path is the path through
Q42: The _ for an activity is the
Q43: Speeding up the project is referred to
Q44: delay in the critical path delays the
Q45: _ is the amount of time that
Q47: There is _ associated with any feasible
Q48: LF - latest finish time can be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents