When Planning an EC Project,planners Must First Consider

Question 27

Multiple Choice

When planning an EC project,planners must first consider:


A) the cost of implementing the project.
B) the existing computer resources available for the project.
C) how the EC project aligns with the organization's overall business plans and processes.
D) a timeline for completion and implementation.

Correct Answer: