Assume an order-requirement digraph has a critical path with length 40 minutes. Based on this information, when the digraph is scheduled on four machines, how much time will be required?
A) Exactly 10 minutes
B) Exactly 30 minutes
C) At least 40 minutes
D) Exactly 40 minutes