Melrose Corporation makes a product that uses a material with the following standards:
The company budgeted for production of 5,800 units in September, but actual production was 5,900 units. The company used 50,210 pounds of direct material to produce this output. The company purchased 55,100 pounds of the direct material at $5.80 per pound.
The direct materials purchases variance is computed when the materials are purchased.
-The materials quantity variance for September is:
A) $3,770 F
B) $3,900 U
C) $3,770 U
D) $3,900 F
Correct Answer:
Verified
Q39: The Fischer Corporation uses a standard costing
Q40: The Hanson Corporation employs a standard costing
Q41: The following materials standards have been established
Q42: Suski Corporation has a standard cost system
Q43: Stench Foods Corporation uses a standard cost
Q45: At Cady Corporation, maintenance is a variable
Q46: Imrie Corporation makes a product that uses
Q47: The following standards for variable manufacturing overhead
Q48: Schley Corporation applies manufacturing overhead to products
Q49: Canevari Corporation makes a product that uses
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents