The Maxwell Corporation has a standard costing system in which variable manufacturing overhead is assigned to production on the basis of standard machine-hours. The following data are available for July:
• Actual variable manufacturing overhead cost incurred: $22,620
• Actual machine-hours worked: 1,600 hours
• Variable overhead rate variance: $3,420 Unfavorable
• Total variable overhead spending variance: $4,620 Unfavorable
-The variable overhead efficiency variance for July is:
A) $8,040 Unfavorable
B) $8,040 Favorable
C) $1,200 Unfavorable
D) $1,200 Favorable
Correct Answer:
Verified
Q172: Bronfenbrenner Co. uses a standard cost system
Q173: The following standards have been established for
Q174: The following labor standards have been established
Q175: Sizzle Company uses a standard cost system
Q176: The following data have been provided by
Q178: Rardin Corporation makes a product with the
Q179: Graybeal Corporation makes a product with the
Q180: The following data have been provided by
Q181: The following data have been provided by
Q182: Shawl Corporation's variable overhead is applied on
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents