Fuhrer Hotel bases its budgets on guest-days. The hotel's static budget for December appears below: The total overhead cost at an activity level of 7,500 guest-days per month should be:
A) $227,250
B) $215,140
C) $216,140
D) $206,040
Correct Answer: