The general requirements for a liquidated damages clause to be enforceable are that:
A) Actual damages are difficult to determine and the liquidated damages amount is reasonable.
B) Actual damages exceed the amount foreseen by the parties.
C) The liquidated damages clause applies only to unforeseeable damages.
D) The breaching party used its best efforts to avoid a breach of the contract.
E) The parties have rescinded the contract.
Correct Answer:
Verified
Q18: Cases involving nominal damages are generally brought
Q36: Equitable remedies are available if there has
Q39: A contract that has been fully performed
Q41: George,an employee,breaches a fixed-term employment contract by
Q44: Under which kind(s)of performance by the other
Q45: Which of the following types of damages
Q46: What does the term "mitigation" refer to
Q47: Damages that are fixed in the contract
Q48: Another term for consequential damages is:
A)Special.
B)Remedial.
C)Liquidated.
D)Nominal.
E)Distinguishable.
Q81: What distinguishes an anticipatory breach from other
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents