Liquidated Damages Under the UCC

Question 41

Multiple Choice

Liquidated damages under the UCC:


A) Are not permissible.
B) Are not permissible anytime both parties have agreed to them.
C) Are permissible only if other remedies are inadequate.
D) Are permissible if reasonable,considering actual damages and the difficulties in computing actual damages.

Correct Answer:

verifed

Verified