Summerlin Company budgeted 4,000 pounds of material costing $5.00 per pound to produce 2,000 units.The company actually used 4,500 pounds that cost $5.10 per pound to produce 2,000 units.What is the direct materials quantity variance?
A) $400 unfavorable.
B) $450 unfavorable.
C) $2,500 unfavorable.
D) $2,550 unfavorable.
E) $2,950 unfavorable.
Correct Answer:
Verified
Q42: Based on a predicted level of production
Q55: A company's flexible budget for 12,000 units
Q77: Based on a predicted level of production
Q78: Georgia,Inc.has collected the following data on one
Q81: A job was budgeted to require 3
Q83: Hassock Corp.produces woven wall hangings.It takes 2
Q84: Use the following data to find the
Q85: The standard materials cost to produce 1
Q86: A job was budgeted to require 3
Q87: The standard materials cost to produce 1
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents