Which of the following is a correct equation to solve for the NPV of the project that has an initial outlay of $30,000, followed by incremental cash inflows in the next 3 years of $15,000, $20,000, and $30,000? Assume a discount rate of 10%.
A) NPV = - $30,000 + $15,000(1.10) 1 + $20,000(1.10) 2 + $30,000(1.10) 3
B) NPV = - $30,000 + $15,000/(1.10) 1 + $20,000/(1.10) 2 + $30,000/(1.10) 3
C) NPV = - $30,000 + $15,000/(1.01) .10 + $20,000/(1.02) .10 + $30,000/(1.03) .10
D) NPV = - $30,000 + $15,000/(1.1) .10 + $20,000(1.2) .10 + $30,000(1.3) .10
Correct Answer:
Verified
Q35: Project Eh! requires an initial investment of
Q36: Project H requires an initial investment of
Q37: Project H requires an initial investment of
Q38: A machine has a cost of $5,575,000.
Q39: A machine has a cost of $5,375,000.
Q41: If a project has a profitability index
Q42: A project has an initial outlay of
Q43: Dieyard Battery Recyclers is considering a project
Q44: Equipment should be replaced whenever replacement results
Q45: Your company is considering a project with
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents