A process costing system differs from a job order costing system in that:
A) There is no need for overhead application rates in process costing systems.
B) Process costing systems are used primarily in service industries,whereas job order costing systems are used in manufacturing operations.
C) Per-unit costs are not computed in process costing systems.
D) Process costing systems are used when production involves large volumes of standardized products,whereas job order costing systems are used when each job or batch of products is uniquely different.
Correct Answer:
Verified
Q30: [The following information applies to the questions
Q31: Which company would most likely not use
Q32: Process costing systems:
A)Are used when companies produce
Q33: For which of the following categories is
Q34: All of the following are characteristics of
Q36: [The following information applies to the questions
Q37: [The following information applies to the questions
Q38: In a production cost report,the units transferred
Q39: Process costing would be suitable for:
A)Automobile repair.
B)Production
Q40: The Work in Process - Assembly account
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents