Yankee Construction Agreed to Lease Payments of $762

Question 39

Essay

Yankee Construction agreed to lease payments of $762.79 on construction equipment to be made at the end of each month for six years. Financing is at 15% compounded monthly.
a) What is the value of the original lease contract?
b) If, due to delays, the first eight payments were deferred, how much money would be needed after nine months to bring the lease payments up to date?
c) How much money would be required to pay off the lease after nine months?
d) If the lease were paid off after nine months, what would the total interest be?
e) How much of the total interest would be due to deferring the first eight payments?

Correct Answer:

verifed

Verified

a) PVn = 762.79 blured image = 762.79(47.2924743) = $...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents