Which of the following is a correct equation to solve for the NPV of the project that has an initial outlay of $30,000, followed by incremental cash inflows in the next three years of $15,000, $20,000, and $30,000? Assume a discount rate of 10%.
A) NPV = −$30,000 + $15 000(1.10) 1 + $20 000(1.10) 2 + $30 000(1.10) 3
B) NPV = −$30,000 + $15 000/(1.10) 1 + $20 000/(1.10) 2 + $30 000/(1.10) 3
C) NPV = −$30,000 + $15 000/(1.01) .10 + $20 000/(1.02) .10 + $30 000/(1.03) .10
D) NPV = −$30,000 + $15 000/(1.1) .10 + $20,000(1.2) .10 + $30,000(1.3) .10
Correct Answer:
Verified
Q21: Which of the following statements is correct?
A)
Q27: Project H requires an initial investment of
Q28: Coastline Project has an initial outlay of
Q29: Cloud Inc is considering a project with
Q32: Suppose you determine that the NPV of
Q33: A machine has a cost of $5,575,000.It
Q34: Project H requires an initial investment of
Q36: Parkway Car can purchase a new vehicle
Q37: The present value of the total costs
Q54: Which of the following is a correct
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents