In a network diagram,an "activity"
A) is the largest unit of work effort consuming both time and resources that a project manager can Schedule and control.
B) is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control.
C) should always be something the company has had experience with.
D) must always have a single, precise estimate for the time duration.
Correct Answer:
Verified
Q32: The earliest start time for an activity
Q33: A project has three paths.A-B-C has a
Q38: In an activity-on-node [AON] network,the nodes represent
Q43: The crash cost is the additional cost
Q48: Before beginning to create a PERT/CPM network
Q50: Which of the following statements concerning the
Q51: Which one of the following statements about
Q66: Of the four major phases in project
Q67: All activities on the critical path must
Q76: For controlling projects, the Cost Performance Index
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents