Which one of the following statements about network diagrams is TRUE?
A) In an activity-on-node diagram, the nodes depict precedence relationships as well as activities.
B) In an activity-on-arc diagram, the arcs depict the activities as well as the precedence relationships.
C) In an activity-on-node diagram, "events" are used to denote the end points of arcs.
D) In an activity-on-arc diagram, there is never a need to use "dummy" activities.
Correct Answer:
Verified
Q32: The earliest start time for an activity
Q33: A project has three paths.A-B-C has a
Q43: The crash cost is the additional cost
Q48: Before beginning to create a PERT/CPM network
Q50: Which of the following statements concerning the
Q52: In a network diagram,an "activity"
A) is the
Q66: Of the four major phases in project
Q67: All activities on the critical path must
Q75: The correct sequence of the four major
Q76: For controlling projects, the Cost Performance Index
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents