In 2011,Huxley Corp.began construction work under a three-year contract.The contract price is $800,000.Huxley used the percentage-of-completion method for financial accounting purposes.The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract.The financial presentations relating to this contract at December 31,2014,appear below. How much cash was collected in 2014 on this contract?
A) $32,000
B) $35,000
C) $47,000
D) $50,000
Correct Answer:
Verified
Q18: A company providing maintenance services on equipment
Q19: If the completed-contract method is used,what is
Q20: Which of the following types of service
Q21: A company uses the percentage-of-completion method to
Q22: The following data relate to a construction
Q24: Sunfish Construction Company uses the percentage-of-completion method
Q25: Astor Construction Company uses the percentage-of-completion method
Q26: Gunner Construction,Inc.has consistently used the percentage-of-completion method
Q27: The following data relate to a construction
Q28: For a construction firm using the completed-contract
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents