Solved

When a Contracting Party Runs into Unforeseeable Difficulties That Make

Question 29

Multiple Choice

When a contracting party runs into unforeseeable difficulties that make his or her performance impossible, courts will:


A) not enforce a modification that is not supported by new consideration.
B) prosecute the contracting party on criminal charges.
C) enforce a modification in the interest of fairness.
D) will make the contracting party pay up in full.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents