If the early start for activity A is equal to 23 months and the duration of activity A is equal to 5 months, what is the earliest finish for activity A?
Correct Answer:
Verified
Q36: An AOA network will never require dummy
Q37: Crashing cost is always higher than the
Q38: The early start of an activity that
Q39: A work breakdown structure is a useful
Q40: The expected project completion time is assumed
Q42: The critical path activities have no _.
Q43: Consider the following network. Q45: _ is the amount of time an Q46: Refer to the table below to Q136: What is the critical path for this
![]()