A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:
A) 6.0
B) 6.33
C) 7.0
D) 7.5
Correct Answer:
Verified