A firm has prepared the following binary integer program to evaluate a number of potential locations for new warehouses. The firm's goal is to maximize the net present value of their decision while not spending more than their currently available capital.
Max 20x1 + 30x2 + 10x3 + 15x4
s.t. 5x1 + 7x2 + 12x3 + 11x4 ? 21 {Constraint 1}
X1 + x2 + x3 + x4 ? 2 {Constraint 2}
X1 + x2 ? 1 {Constraint 3}
X1 + x3 ? 1 {Constraint 4}
X2 = x4 {Constraint 5}
Which of the constraints enforces a contingent relationship?
A) Constraint 1
B) Constraint 2
C) Constraint 3
D) Constraint 4
E) Constraint 5
Correct Answer:
Verified
Q27: Which of the following techniques or tools
Q28: Note: This problem requires the use
Q29: In a BIP problem, 1 corresponds to
Q30: When binary variables are used in a
Q31: If a firm wishes to choose at
Q33: A firm has prepared the following
Q34: In a BIP problem with 2 mutually
Q35: Binary integer programming problems can answer which
Q36: In a BIP problem with 3 mutually
Q37: In a crew scheduling problem there is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents