The operations manager for the Blue Moon Brewing Co. produces two beers: Lite (L) and Dark (D) . He can only get 675 gallons of malt extract per day for brewing and his brewing hours are limited to 8 hours per day. To produce a keg of Lite beer requires 2 minutes of time and 5 gallons of malt extract. Each keg of Dark beer needs 4 minutes of time and 3 gallons of malt extract. Profits for Lite beer are $3.00 per keg and profits for Dark beer are $2.00 per keg. The brewery's goal is to maximize profits.
What is the objective function?
A) P = 2L + 3D.
B) P = 2L + 4D.
C) P = 3L + 2D.
D) P = 4L + 2D.
E) P = 5L + 3D.
Correct Answer:
Verified
Q43: Which of the following constitutes a simultaneous
Q44: The production planner for Fine Coffees, Inc.
Q45: Which objective function has the same slope
Q46: Given the following 2 constraints, which solution
Q47: Use the graphical method for linear
Q49: Given the following 2 constraints, which solution
Q50: Which of the following constitutes a simultaneous
Q51: Solving linear programming problems graphically
A) is possible
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents