Question 29

Multiple Choice

Why is the budget variance the real control variance, for fixed overhead?


A) It compares budgeted expenditures with budgeted fixed overhead costs.
B) It compares actual expenditures with budgeted fixed overhead costs.
C) It compares actual expenditures with budgeted variable overhead costs.
D) It compares the static budget with the flexible budget.

Correct Answer: