Bret decided to enlarge the fishpond in his backyard. He contracted with a general contractor, Conan. Conan subcontracted with Darson to do the excavation and with Ericson to do the plumbing. Conan's own workers did the masonry work. Bret made "progress payments" to Conan, since Conan said such payments were necessary to pay his workers and subcontractors. Bret learned that the workers and subcontractors had not been paid; Conan had used the payments to pay debts unrelated to the job on Bret's pond. Which of the following best describes Bret's position?
A) Bret will be liable for all unpaid amounts, because the work was on his land and for his benefit.
B) If Bret held back the 10% required by statute from his payments to Conan, but then later paid it out despite liens having been filed against his property, Bret would still face no liability as he technically complied with the legislation.
C) Because of the doctrine of privity of contract, Bret will not face any liability whatsoever.
D) If Bret held back the 10% required by statute from his payments to Conan, his obligation would generally be limited to the amount of that holdback.
E) Bret had no obligation to hold back any amount of the payments made to Conan as the hold back requirement doesn't apply to progress payments.
Correct Answer:
Verified
Q8: Which one of the following is true
Q9: With regard to conditional sales and chattel
Q10: Which of the following is a goal
Q11: Hank sold three properties for Mr. W
Q12: Holtz hires Joe, a builder, to convert
Q14: Which of the following is governed by
Q15: Which one of the following actions by
Q16: With regard to bankruptcy and debt collection,
Q17: Which of the following is false with
Q18: If you want to buy a car
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents