An assembly line consists of 158 tasks grouped into 32 workstations.The sum of all task times is 105 minutes.The largest assigned cycle time is 4 minutes.What is the efficiency of this line?
A) 8 percent
B) 21 percent
C) 82 percent
D) 100 percent
E) 81 percent
Correct Answer:
Verified
Q130: An assembly line has been designed to
Q132: An assembly line consists of 21 tasks
Q133: A company is designing a product layout
Q134: Develop a solution for the following line
Q136: You have been asked to balance a
Q137: Cyclone Appliances has developed a new European-style
Q139: An electronics manufacturer makes remote control devices
Q283: If a layout problem is solved by
Q296: Which of the following is NOT a
Q310: Identify the five common layout heuristics used