The critical path for the network activities shown below is ________ with duration ________. 
A) A-B-D; 10
B) A-B-E; 11
C) C-E; 12
D) A-D-E; 13
E) A-B-C-D-E; 22
Correct Answer:
Verified
Q24: Identify each of the purposes of project
Q30: PERT, but not CPM, has the ability
Q41: A simple CPM network has five activities,A,B,C,D,and
Q46: Every network has at least one critical
Q51: Which of the following statements regarding critical
Q53: Activity D on a CPM network has
Q56: The main difference between PERT and CPM
Q58: What is the basic difference between PERT
Q59: The ES of an activity that has
Q71: _ is the amount of time an