The network below represents a project being analyzed by the critical path method.Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=10,and J=6. a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q61: Explain why the critical path is the
Q63: Draw the AOA and AON networks for
Q64: Given the project within the table below,calculate
Q66: What are the earliest activity start time
Q67: The network below represents a project being
Q69: The standard deviation of project duration is
Q70: Consider the network presented in the following
Q80: The PERT pessimistic time estimate is an
Q84: The beta distribution is used in project
Q99: The beta distribution is used in project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents