Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.
A) One; $400
B) One; $6,800
C) Two; $1,000
D) Two; $5,000
E) One or Two should be crashed; $1,400
Correct Answer:
Verified
Q109: A project manager is interested in crashing
Q110: Which of these statements regarding time-cost tradeoffs
Q112: In project management, crashing an activity must
Q113: What was the name of the construction
Q114: Pirmin's Bike Shop is behind on a
Q120: If an activity whose normal duration is
Q122: Which of the following is NOT a
Q125: A network has been crashed to the
Q127: Identify several advantages of using PERT (and
Q129: _ is decreasing activity time in a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents